The figure below shows the process of matching and claiming to be followed for making claims EnergyTag Compliant. 

...

Info

Matching and Claim Verification Explained

  • GC Matching (or Granular Matching or Matching): Allocating Attributes of canceled GCs to a corresponding quantity of consumed energy, for well-specified Matching Features.

  • Temporal Matching (or GC Temporal Matching: Associating the period of time during which energy is produced or stored and which has been recorded on the GC at its Issuance with the corresponding time at which the GC is canceled and the energy is consumed. The time interval is equal to or less than 60 minutes and evidence of energy production and consumption is provided by GCs.

  • Geographical Matching (or GC Geographical Matching): Associating the geographical location of energy production or storage which has been recorded on a GC at its Issuance, with the geographical location of energy consumption and for which the GC is canceled. For example, Geographical Matching may take place within physically interconnected zone(s) or Bidding Zone(s).

  • GC Matching Claim (or Matching Claim): A statement by a Consumer or Supplier of energy regarding the proportion of their consumption being matched to GCs, and the resulting Attributes allocated to this consumption.

...